For two decades, technical communicators have turned to TechWhirl to ask and answer questions about the always-changing world of technical communications, such as tools, skills, career paths, methodologies, and emerging industries. The TechWhirl Archives and magazine, created for, by and about technical writers, offer a wealth of knowledge to everyone with an interest in any aspect of technical communications.
Structuring payment schedule based on doc deliverables
Subject:Structuring payment schedule based on doc deliverables From:Johanna <chazjo -at- magma -dot- ca> To:"TECHWR-L" <techwr-l -at- lists -dot- raycomm -dot- com> Date:Fri, 09 Mar 2001 17:05:13 -0500
I am writing up an estimate for a fixed-price project
and I want to breakdown the payment schedule to
reflect the project deliverables. I am producing two
user manuals from scratch in a fairly short period of
time (less than 8 weeks). A fellow freelancer
suggested the following payment schedule:
Start of project - 20%
Installation manual draft - 20%
User guide draft - 20%
Installation manual final - 20%
Installation manual final - 20%
The problem I have with this is that I often work on
documents concurrently and will get the client to
begin reviewing before I am finished with the "draft".
Does anyone else have suggestions?
IPCC 01, the IEEE International Professional Communication Conference,
October 24-27, 2001 at historic La Fonda in Santa Fe, New Mexico, USA.
CALL FOR PAPERS OPEN UNTIL MARCH 15. http://ieeepcs.org/2001/
---
You are currently subscribed to techwr-l as: archive -at- raycomm -dot- com
To unsubscribe send a blank email to leave-techwr-l-obscured -at- lists -dot- raycomm -dot- com
Send administrative questions to ejray -at- raycomm -dot- com -dot- Visit http://www.raycomm.com/techwhirl/ for more resources and info.