RE: Estimation of Timelines for Documentation Projects
From: "David Locke" <dlocke -at- texas -dot- net>
To: "Vlad Dracul" <vladvampiredracul -at- hotmail -dot- com>
Subject: RE: Estimation of Timelines for Documentation Projects
Date: Mon, 6 Oct 2003 06:03:43 -0500
But, that is just the first estimate. There is the second estimate, the
detailed, post-analysis estimate. This estimate is built on a detailed view
of what you will have to produce: how many pages, how many graphics, how
much front-matter, how much back-matter, the development schedule, source
quality, writer quality, editor quality, production quality, infrastructure,
stability of the production platform,.... You take the counts be they pages,
function points, dialogs and controls, paragraphs, what have you, and use
them as a multiplier for the production standard. The production standard
comes from prior project histories. If you have no histories, make sure you
start collecting the data: what kind of work, how much, how long did it
take. When the averages converge, start over. And, in the absence of
histories or metrics covering your own processes, use industry numbers.
Realize that industry numbers are not competitive, so they won't work in
competitive situations.
A very good book was Schultz'es book, "The Business of Writing." Another is
"Controlling Software Projects." Another just for edification it Bohem's
"Software Economics," or "COMOCO II."
David Locke
_________________________________________________________________
MSN 8 helps eliminate e-mail viruses. Get 2 months FREE*. http://join.msn.com/?page=features/virus
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
NEED TO PUBLISH YOUR FRAMEMAKER CONTENT ONLINE?
RoboHelp for FrameMaker is a NEW online publishing tool for FrameMaker that
lets you easily single-source content to online Help, intranet, and Web.
The interface is designed for FrameMaker users, so there is little or no
learning curve and no macro language required! Call 800-718-4407 for
competitive pricing or view a live demo at: http://www.ehelp.com/techwr-l3
---
You are currently subscribed to techwr-l as:
archive -at- raycomm -dot- com
To unsubscribe send a blank email to leave-techwr-l-obscured -at- lists -dot- raycomm -dot- com
Send administrative questions to ejray -at- raycomm -dot- com -dot- Visit
http://www.raycomm.com/techwhirl/ for more resources and info.
Previous by Author:
Estimation of Timelines for Documentation Projects
Next by Author:
Pointers on Information Mapping
Previous by Thread:
Re: Estimation of Timelines for Documentation Projects
Next by Thread:
Estimation of timelines for documentation projects?
Search our Technical Writing Archives & Magazine
Visit TechWhirl's Other Sites
Sponsored Ads